WEATHERSFIELD VT-131

NH SURF(85) Weathersfield

Resurfacing VT 131 in Weathersfield from Town MM 8.145 to Town MM 8.647, and VT12 from Town MM 0.000 to Town MM 0.394

Project Location

Beginning in the Weathersfield at MM 8.120 (near the Exit 8 Interchange on I-91) and extending easterly along VT Route 131 for a distance of 0.510 miles and stopping at MM 8.630 at the intersection of US Route 5, VT 131 and VT Route 12.  Resuming at MM 0.018 (at the bridge which spans the Connecticut River) on VT Route 12 and extending northerly 0.394 miles to mile MM 8.630 on VT Route 131.

Project Scope

This project will involve 3/4" of milling and paving with a thin overlay treatment.  Prior to paving, the the roadway will be crack sealed and small isolated areas will be repaired.    

Project Timeline

The project will begin construction in the spring months of 2022 and conclude in the summer months of 2022.  Nght work is not anticipated, expect periods of one-way alternating traffic.  This project will be constructed with the Weathersfield STP SURF(80) project.   


Contact Information

**Please note: Contractors are to direct all inquiries to Contract Administration during project advertisement.

VTrans Project Manager
Brandon Kipp
(802) 224-6110
brandon.kipp@vermont.gov

VTrans Resident Engineer
William Waite
william.waite@vermont.gov

Contact VTrans