WEATHERSFIELD VT-131

STP SURF(80) Weathersfield

Resurfacing VT131 in Weathersfield from Town MM 1.324 to Town MM 8.145, including associated approaches

Project Location

Beginning in the Town of Weathersfield at MM 1.326 (at the intersection of VT Route 106) and extending easterly along interstate route 131 for a distance of 6.794 miles to MM 8.120 (near the Exit 8 I-91 interchange).  

Project Scope

This project will involve 3/4" of milling and paving with a thin overlay treatment.  Prior to paving, the the roadway will be crack sealed and small isolated areas will be repaired.  

Project Timeline

The project will begin construction in the spring months of 2022 and will conclude in the summer months of 2022.  All work will be performed during daylight hours.  Expect periods of one-way alternating traffic.  This project will be constructed with the Weathersfield NH SURF(85) project under the same contract. 


Contact Information

**Please note: Contractors are to direct all inquiries to Contract Administration during project advertisement.

VTrans Project Manager
Brandon Kipp
(802) 224-6110