ESSEX-COLCHESTER VT-2A
STP 0207(4) Essex
Resurfacing of VT2A from ETE MM 9.015 to ETE MM 13.840. Also includes 0.140 mile of VT127.
Project Location: The project begins at the Class 1 limit on VT Route 2A in Essex and extends along VT Route 2A to its intersection with US Route 7 in Colchester. Work will also take place on VT Route 127 between its intersections with US Route 7 and VT Route 2A.
Project Description: Work will consist of coarse-milling the existing pavement to a 2” depth, then placing a 1/2” lift of Type IVS pavement to level the road surface, followed but a 1-1/2” lift of Type IVS pavement as the final wearing surface. Additionally, some guardrail work will be performed to repair and replaced damaged sections to bring full runs into compliance with the current standards. Shoulder berms that have built up will be removed to facilitate better drainage from the road surface, and some ditching work may be performed to further aid in drainage.
The corridor will be evaluated for the installation of Centerline Rumble Strips (CLRS). CLRS will be installed where the speed limit is 45 MPH or greater, the pavement width is 14 feet in both directions, and the traffic volume exceeds 1500 vehicles per day. The CLRS will be stopped at Town Highway intersections, and anywhere that a residence falls within 100 feet of centerline. In these cases, the CLRS will be stopped and resumed 100 feet from either corner of the residence.
Note that this project will be advertised as a composite contract with the Essex NH 033-1(26) project, which will pave VT Route 289.
Contact Information
**Please note: Contractors are to direct all inquiries to Contract Administration during project advertisement.
Public Information Consultant
Stephanie Barrett
(802) 399-7847
sbarrett@coibsinc.com