WOODSTOCK-HARTLAND US-4

NH FPAV(50) Woodstock

District paving on US 4 from Woodstock MM 6.96 to Hartland MM .5.

Project Location: Work begins at the Class 1 Limit on US Route 4 in Woodstock and continues easterly along US Route 4 to its intersection with VT Route 12 South in Hartland.

Project Description: Work on this project will consist of milling the pavement to a 1.5” depth, spot shimming and surface prepping, then paving with a 1.5” lift of Type IVS wearing course pavement. Additionally, some guardrail work will be performed to repair and replaced damaged sections to bring full runs into compliance with the current standards. Shoulder berms that have built up will be removed to facilitate better drainage from the road surface, and some ditching work may be performed to further aid in drainage.

The corridor will be evaluated for the installation of Centerline Rumble Strips (CLRS). CLRS will be installed where the speed limit is 45 MPH or greater, the pavement width is 14 feet in both directions, and the traffic volume exceeds 1500 vehicles per day. The CLRS will be stopped at Town Highway intersections, and anywhere that a residence falls within 100 feet of centerline. In these cases, the CLRS will be stopped and resumed 100 feet from either corner of the residence.


Contact Information

**Please note: Contractors are to direct all inquiries to Contract Administration during project advertisement.

Public Information Consultant
Delia Makhetha
(603) 263-8881
delia.makhetha@wsp.com

Contact VTrans