HALIFAX-WHITINGHAM VT-112

STP FPAV(47) Halifax

Resurfacing along VT 112 from Halifax ETE MM 0.0 to Whitingham ETE MM 7.45.

Project Location: Work will begin at the Massachusetts/Vermont boarder and will extend northerly along VT Route 112 for approximately 7.5 miles to the intersection of VT Route 112 and VT Route 100 in Whitingham.

Project Description: Work on this project will consist of milling the pavement to a 1.5” depth, spot shimming and surface prepping, then paving with a 1.5” lift of Type IVS wearing course pavement. Additionally, some guardrail work will be performed to repair and replaced damaged sections to bring full runs into compliance with the current standards. Shoulder berms that have built up will be removed to facilitate better drainage from the road surface, and some ditching work may be performed to further aid in drainage.

The corridor will be evaluated for the installation of Centerline Rumble Strips (CLRS). CLRS will be installed where the speed limit is 45 MPH or greater, the pavement width is 14 feet in both directions, and the traffic volume exceeds 1500 vehicles per day. The CLRS will be stopped at Town Highway intersections, and anywhere that a residence falls within 100 feet of centerline. In these cases, the CLRS will be stopped and resumed 100 feet from either corner of the residence.


Contact Information

**Please note: Contractors are to direct all inquiries to Contract Administration during project advertisement.

VTrans Project Manager
Matthew Bogaczyk
(802) 793-5321
matthew.bogaczyk@vermont.gov

VTrans Resident Engineer
Sheamus Fagan
(802) 498-8751
sheamus.fagan@vermont.gov

Contact VTrans