HARTLAND BRIDGE BR#3

BF 0153(1) Hartland

Project is to replace the existing concrete deck of Br. 3 on VT-12 in Hartland over the Lulls Brook with a new concrete deck with including minor widening. A temporary traffic pattern of one-lane of alternating traffic has been installed by District forces to be in place until the bridge deck replacement project occurs.

A full depth hole has developed in this bridge deck late in the fall of 2020. A project is being quickly developed to replace the entire concrete bridge deck with minor widening.


One lane of alternating traffic is currently being maintained on the existing bridge. The bridge will be closed to vehicular and pedestrian traffic during construction of the new concrete deck.


Link to project SharePoint site: https://outside.vermont.gov/agency/vtrans/external/Projects/Structures/20b326




Closures:

  • VT-12 will be closed at Bridge BR#3 over LULLS BROOK for 21 days between September 7, 2021 and September 27, 2021.

Contact Information

**Please note: Contractors are to direct all inquiries to Contract Administration during project advertisement.

Public Information Consultant
Nick Charyk
(603) 420-9482
nicholas.charyk@wsp.com

Contact VTrans