NORWICH-THETFORD US-5
STP FPAV(30) Norwich
Paving along US 5 from Norwich mm 2.4 to Thetford mm 3.4.
Project Location:
Beginning on US Route 5 in the Town of Norwich at MM 2.40 (near the intersection of River Road) and extending northerly along US Route 5 for a distance of 9.290 miles to MM 3.400 in the Town of Thetford (1/4 mile south of Sanborn Rd.).
Project Description:
Work to be performed includes paving the existing highway, guardrail, pavement markings, centerline rumble strips (CLRS) and other highway related items.
Project Timeline:
Construction will begin in the spring months of 2021 and will conclude in the summer months of 2021.
Contact Information
**Please note: Contractors are to direct all inquiries to Contract Administration during project advertisement.
VTrans Project Manager
Brandon Kipp
(802) 224-6110
brandon.kipp@vermont.gov
VTrans Resident Engineer
William Waite
william.waite@vermont.gov