VERGENNES VT-22A

STP PC20(1) Vergennes

Class 1 paving in Vergennes on VT 22A and Ferrisburgh State Highway

Project Locations:

Beginning on VT Route 22A in the Town of Vergennes at the town line with Panton at mile marker 0.000 and running northerly along VT Route 22A for a distance of 2.189 miles and stopping at the town line with Ferrisburgh at mile marker 2.189. Also, beginning at VT Route 22A mile marker 1.233 the project continues easterly along Ferrisburgh State Highway (Green Street) for a distance of 0.666 miles and stops in Vergennes at mile marker 0.666 in the intersection of US Route 7.

Project Description:

Work will generally consist of coarse milling the existing pavement to a 2” depth, then placing a 1/2” lift of Type IVS pavement to level the road surface, followed by a 1-1/2” lift of Type IVS pavement as the final wearing surface. Prior to the placement of the final wearing surface utility valves and drainage structures within the roadway will be adjusted as necessary. Sidewalk ramps and pedestrian crossing infrastructure will be replaced and upgraded to meet current ADA standards. Some minor drainage work will occur near and along the edge of pavement. Signs will also be replaced and upgraded as necessary to meet current specifications in the Manual on Uniform Traffic Control Devices (MUTCD).  Existing traffic signals within the project limits will receive some minor upgrades.  This project is incorporated under a larger composite contract with the Bristol STP PC20(2) Class I paving project.

This project is also incorporating various features which were identified within the VT 22A Truck Route Study which was prepared by Addison County Regional Planning Commission.  A link to the Final Report can be found below.  This project will be incorporating most of the proposed features which were identified under "Alternative A - Inline Alternative". 

http://acrpc.org/programs-services/transportation/transportation-projects/

Project Timeline:

Work will begin in the spring months of 2020 and will end in the fall of 2020.  The majority of the work between mile marker 1.033 (Bridge 27 over the Otter Creek River) to mile marker 1.306 (near City Hall) on VT Route 22A be performed between the hours of 9:00 pm to 8:00 am in the next calendar day.


Contact Information

**Please note: Contractors are to direct all inquiries to Contract Administration during project advertisement.

Public Information Consultant
Natalie Boyle
(802) 855-3893
nboyle@eivtech.com

Contact VTrans