ORWELL VT-22A
STP 017-1(18) Orwell
Work consist of shoulder reconstruction and widening of the roadway from 10-foot lanes and 2-foot shoulders to 11-foot lanes and 6-foot shoulders while also reclaiming the existing roadway with a stabilized base in Orwell along VT 22A from MM 0 to MM 3.22.
This project will include partial reconstruction and shoulder reconstruction and widening of VT Route 22A beginning at the Benson and Orwell Town line and will extend North 3.220 miles to the intersection of VT Route 22A and VT Route 73.
Traffic Management will be reviewed as project progresses through the design phases.
Contact Information
**Please note: Contractors are to direct all inquiries to Contract Administration during project advertisement.
VTrans Project Manager
Bruce Martin
(802) 595-9653
bruce.b.martin@vermont.gov