BARRE TOWN-ORANGE US-302

STP PS23(1) Barre Town

Resurfacing on US 302 from Barre Town mm 0 to Orange mm 6.092.

Project Location:  The project begins at the Barre City/Barre Town townline line and extends easterly 9 miles to a point near the VT Route 25 intersection in the Town of Orange.  The project is also part of a larger contract with the Orange-Topsham STP FPAV(56) project which is also located on US Route 302. 

Project Scope:  The project involves milling and resurfacing the top 2" of exsting pavement, centerline rumble stripes, line striping, new signs, guardrail rehabilitation and drainage improvements.  It is anticipated that one-way alternating traffic will be the primary impact to the traveling public during construction.

Project Timline:  The project will begin construction in the spring months of 2025 and will conclude in the fall months of 2025. 


Contact Information

**Please note: Contractors are to direct all inquiries to Contract Administration during project advertisement.

Public Information Consultant
Toni Marie Pignatelli
(802) 267-7717
toni.m.pignatelli@imegcorp.com

Contact VTrans