BETHEL BRIDGE BR#38

BHF 0241(38) Bethel

REPLACEMENT OF BRIDGE NO. 38 ON VT12 IN BETHEL, OVER GILEAD BROOK.

Project Location: Town of Bethel in Windsor County on VT 12 over Gilead Brook. The bridge is located approximately 4 miles north of the intersection of VT 12 and VT 107.

The Bethel VT 12 Bridge 38 project will replace the existing bridge, which has a nonstandard width and is nearing the end of its design life. The existing bridge, constructed in 1928, is a four-span, two-lane structure with a length of 326 feet and roadway clear width of 20 feet. The superstructures of the two 120’-2” interior spans are steel deck trusses. The concrete deck was last replaced in 1971 and is in need of replacement.

VTrans evaluated alternatives for replacement of the Bethel VT 12 Bridge 38 in an engineering study completed in May 2014. The study addressed the proposed design criteria for bridge and roadway alignment, right-of-way impacts, hydraulics, historical and archaeological resources, and historic aesthetic requirements. Several alternatives were considered including no action, rehabilitation, and complete bridge replacement. Strengthening the truss members to meet current and future design loads was determined to be economically unfeasible. Given the age and condition of the structure, the engineering study recommended a complete bridge replacement.

The new three-span bridge will have a weathering steel plate girder superstructure with parabolic haunched webs at the piers for aesthetic purposes. The new bridge will be 364 feet in length including two approach spans of 110 feet and a center span of 144 feet. The clear roadway width of the new bridge will be 31 feet. An ornamental steel lattice treatment similar to that on the existing bridge will be attached to the outside of the standard two rail box beam for aesthetic purposes. The two piers will be concrete hammerhead piers that rise approximately 45 feet above the existing streambed. The piers are located near the edges of the existing channel.

Closure of VT 12 would significantly affect the traveling public and first responders so traffic will be maintained on the existing bridge throughout construction. The new bridge will be constructed just to the west of the existing bridge. To align the existing roadway to the proposed roadway, there will be temporary single-lane closures for paving operations on either end of the bridge. Since traffic is being maintained throughout construction and there are significant project constraints due to the length, height and site, Accelerated Bridge Construction methods are not appropriate for this project.


Traffic Impact: Traffic will be maintained on the existing bridge while the new bridge is constructed upstream of the existing.

Link to project sharepoint site: https://outside.vermont.gov/agency/vtrans/external/Projects/Structures/10c216



Contact Information

**Please note: Contractors are to direct all inquiries to Contract Administration during project advertisement.

Public Information Consultant
Natalie Boyle
(802) 855-3893
nboyle@eivtech.com

Contact VTrans

Technical Documents

The Vermont Agency of Transportation is committed to ensuring accessibility and digital accessibility for all. If you need language assistance, reasonable accommodation, or alternative format, please email AOT Factsheet Support.