PITTSFORD-BRANDON US-7

NH 019-3(494) Pittsford SEGMENT 4 - FORT VENGENCE

RECONSTRUCTION OF US7 IN PITTSFORD AND BRANDON, SEGMENT 4: BEGINNING 1.623 KM SOUTH OF THE PITTSFORD-BRANDON TOWN LINE AND EXTENDING NORTHERLY 2.681 KM. WORK INCLUDES WIDENING, FULL SUBBASE RECONSTRUCTION, DRAINAGE, ETC.

Full depth reconstruction of US 7 beginning just south of the Pomainville Farm/Fort Vengeance Monument and extending northerly approximately 1.67 miles to a point just south of the Otter Valley Union High School (Completed Segment 5). Construction Traffic Management to provide a two way detour(s) through construction zones.


Contact Information

**Please note: Contractors are to direct all inquiries to Contract Administration during project advertisement.

VTrans Project Manager
Casey Leach
(802) 498-8492
casey.leach@vermont.gov

VTrans Resident Engineer
Christopher Williams
(802) 498-4170
christopher.d.williams@vermont.gov

Contact VTrans

The Vermont Agency of Transportation is committed to ensuring accessibility and digital accessibility for all. If you need language assistance, reasonable accommodation, or alternative format, please email AOT Factsheet Support.