KILLINGTON BRIDGE BR#33

BF 020-2(42) Killington

REPLACEMENT OF BRIDGE NO. 33 ON US4 IN KILLINGTON, OVER THE OTTAUQUECHEE RIVER.

VTrans evaluated alternatives for replacement of Bridge 33 in an engineering study completed in November 2014. The study assessed the proposed design criteria for the bridge and roadway alignment, right-of-way impacts,hydraulic capacity, and environmental and cultural resources. Several alternatives were examined including bridge rehabilitation and replacement along with several traffic maintenance options including a short term bridge closure, phased construction and a temporary bridge.

Project Update 08/01/2019

The scope of the project has changed.  Bridge 33 will be completely replaced using conventional construction.  Traffic will be maintained with a temporary bridge. The new bridge will be 73 feet in length and 40 feet wide including two 12 foot travel lanes and two 8 foot shoulders. The new bridge will feature a 3 rail box beam bridge rail with w-beam approach rails terminating beyond the bridge.


Traffic During Construction: A two-way temporary bridge will be constructed upstream of the existing bridge. 

Link to project sharepoint site: https://outside.vermont.gov/agency/vtrans/external/Projects/Structures/13b260


Contact Information

**Please note: Contractors are to direct all inquiries to Contract Administration during project advertisement.

Public Information Consultant
Annabelle N. Dally
(802) 825-2555
annabelle.dally@wsp.com

Contact VTrans

Technical Documents